System updates improve water quality in Villa Grove

VILLA GROVE, ILLINOIS The City of Villa Grove's Water Treatment Plant was built in the late 1930s and has been upgraded through the years, but changes...

Continue reading

Century-old bridge replaced for stability, structure

KENDALL, WISCONSIN PERIOD OF SERVICEJanuary 2018 to June 2018 CONTRACT VALUE$45,000 CONSTRUCTION COST$313,519 SIZELength: 40 feetWidth: 28.5 feet Beth...

Continue reading

Environmental site investigation completed before Morgan Street Bridge replaced

ROCKFORD, ILLINOIS PERIOD OF SERVICESAugust 2011 to April 2014 CONTRACT VALUE$71,710 CONSTRUCTION COST$40,000,000 SIZELength: 503 feetWidth: 73.2 feet...

Continue reading

Auto surveying method used on Savanna-Sabula Bridge reconstruction project

SAVANNA, ILLINOIS  PERIOD OF SERVICESSeptember 2015 to June 2018 CONTRACT VALUE$142,250 CONSTRUCTION COST$80,645,311 SIZELength: 2,600 feetWidth:...

Continue reading

Master Plan revitalizes Oakdale Nature Preserve

FREEPORT, ILLINOIS PERIOD OF SERVICESSeptember 2020 to Present CONTRACT VALUE$98,000 CONSTRUCTION COST$842,000 Oakdale Nature Preserve in Freeport, Il...

Continue reading

Woodward Rock Cut campus features environmental benefits

LOVES PARK, ILLINOIS PERIOD OF SERVICESOctober 2015 to August 2016 CONTRACT VALUESchematic: $38,000Final: $142,000 CONSTRUCTION COST$1,500,000 Woodwar...

Continue reading

Stormwater management part of SwedishAmerican Riverwest Clinic site design

ROCKFORD, ILLINOIS PERIOD OF SERVICESSeptember 2017 to February 2018 CONTRACT VALUE$23,200 CONSTRUCTION COST$7,000,000 SwedishAmerican, a division of ...

Continue reading

Iowa Community Development Block Grant Projects

IOWA COMMUNITY DEVELOPMENT BLOCK GRANT PROJECTS Wellsburg - Wastewater Treatment Plant ImprovementsApproximate Cost - $1,818Construction – In Progress...

Continue reading

Grants help Galena Territory Association improve trails, water quality

GALENA, ILLINOIS PERIOD OF SERVICEAugust 2005 to September 2014 CONTRACT VALUE$15,240  AT A GLANCE» Obtained permits.» Coordinated agreements wit...

Continue reading

Safe drinking water goal with Shannon Water Treatment System upgrades

SHANNON, ILLINOIS PERIOD OF SERVICESAugust 2015 to Present CONTRACT VALUE$240,000 – Design$463,000 – Construction$20,000 – Loan Administration CONSTRU...

Continue reading

Gas utility benefits from land surveying services

CHAMPAIGN, ILLINOIS PERIOD OF SERVICESJune 2018 to March 2019 CONTRACT VALUE$150,000 Since 2011, Fehr Graham surveyors have provided land surveying&nb...

Continue reading

City Engineer: South Beloit, Illinois

SOUTH BELOIT, ILLINOIS PERIOD OF SERVICEJanuary 2013 to Present  AT A GLANCE» Brownfields Work Plan.» Street Maintenance and Reconstruction Desig...

Continue reading

Hybrid solution works for new Coggon Wastewater Treatment Plant

COGGON, IOWA PERIOD OF SERVICENovember 2015 to July 2018CONTRACT VALUE$847,000 CONSTRUCTION COST$3,398,00  AT A GLANCE» Completed Topographic Sur...

Continue reading

Innovation, flexibility goals for new pump station, force main at University of Illinois

URBANA, ILLINOIS PERIOD OF SERVICESNovember 2013 to September 2017 CONTRACT VALUE$1,088,000 CONSTRUCTION COST$7,382,000 Massive high-rise student apar...

Continue reading

Better technology, improved water quality focus for South Beloit Wastewater Treatment Plant

SOUTH BELOIT, ILLINOIS PERIOD OF SERVICESDesign: January 2017 to December 2017Construction: June 2018 to Present CONTRACT VALUE$3,422,000 CONSTRUCTION...

Continue reading

Disposal system helps Village of Royal businesses grow

ROYAL, ILLINOIS PERIOD OF SERVICESApril 2019 to July 2020 CONTRACT VALUE$18,300 CONSTRUCTION COST$200,000 There isn't a sanitary sewer system in the V...

Continue reading

Improvements to Harrison Avenue accommodate urban growth

ROCKFORD, ILLINOIS PERIOD OF SERVICESSeptember 2013 to April 2014 CONTRACT VALUE$1,113,246 The City of Rockford hired Fehr Graham to help reconstruct ...

Continue reading

Masonry investigation at Construction Engineering Research Laboratory

CHAMPAIGN, ILLINOIS PERIOD OF SERVICESJuly 2019 to September 2019 CONTRACT VALUE$8,875 The Construction Engineering Research Laboratory (CERL) and the...

Continue reading

Replacing an 80-year-old bridge

CENTER POINT, IOWA PERIOD OF SERVICESeptember 2017 to November 2017 CONTRACT VALUE$2,500 SIZELength: 21 feetWidth: 24 feet  AT A GLANCE» Preparat...

Continue reading

President Abraham Lincoln's receiving vault restored

SPRINGFIELD, ILLINOIS PERIOD OF SERVICESFebruary 2014 to May 2015 CONTRACT VALUE$56,500 CONSTRUCTION COST$386,000 Time had not been kind to the receiv...

Continue reading